Slide 1GoalCommon Inputs to Project SchedulingWork Breakdown StructureProducing a Documentary DVDCommon Formats for Project SchedulesCommon Formats for Project SchedulesFinding Project Duration using the Network DiagramFinding Project Duration using the Network DiagramThe Project Schedule is…The Project Schedule is… (according to MS Project)Sensitivity AnalysisEstimating task durationsProgram Evaluation and Review Technique (PERT)Let’s revisit our DVD projectThe Project Schedule is for ETCan now answer additional questionsFind1BA 341 – Lean OperationsDr. Bogdan BichescuIntroduction to Project SchedulingGoal Want to identify and use effective tools for planning, scheduling and monitoring project progressWhat should we focus on in projects?Common Inputs to Project SchedulingList of project tasks, subtasks, work packages and activitiesLogical sequence of activities in the projectActivity durationsResources involved and their availabilityUsually presented as Work breakdown structure (WBS)Precedence tablesWork Breakdown StructureProjectMajor TasksSubtasksActivities (Work Packages)Producing a Documentary DVDPrecedence TableActivity Description Predecessor DurationABCDEFGScript writingSchedule shootsScript approvalRevise scriptShootingEditingCover Design ----AABCD, E107571135Common Formats for Project SchedulesGantt chartsHow do we find the project duration?Common Formats for Project SchedulesProject Network DiagramsStart, 0A,10B, 7C, 5D, 7E, 11End, 0F, 3G, 5Activity Name & DurationFinding Project Duration using the Network DiagramOne alternative is to identify all possible paths through the projectProject duration is given by longest path (critical path)No. Path Duration1Start A C F End182Start A D G End223Start B E G End23Critical Path: Start B E G End23Finding Project Duration using the Network DiagramUsing the Critical Path Method (CPM) Start, 00000A, 10111100B, 77070C, 520151510D, 718111710E, 11187187End, 023232323F, 323201815G, 523182318Earliest Start Time (ES)Earliest Finish Time (EF)Latest Start Time (LS)Latest Finish Time (LF)Activity Name & DurationSlack=LS-ES=LF-EFThe Project Schedule is… Using the Critical Path Method (CPM)The Project Schedule is… (according to MS Project)11Sensitivity AnalysisAssuming that all activities start at their earliest times, find the impact on project scheduling if: Activity C takes 7 days?Activity G is delayed to 9 days?Activity D now takes 8 days?Estimating task durationsCPM assumes durations are deterministicIs this realistic?How is it done in practice?Do your normal cautious estimating Add a generous safety marginThen…double it!!TimeProbabilityMost likelyMedianPessimisticOptimistic50% of probabilityProgram Evaluation and Review Technique (PERT)Similar to CPM but able to incorporate duration uncertaintyLet, for each project taska = optimistic time estimateb = pessimistic time estimatem = most likely time estimateThen, compute for each project taskET (Expected Time) = (a + 4m + b)/6σ2 (Variance) = ((b-a)/6)2Let’s revisit our DVD projectActivityOptimistic (a)Most Likely (m) Pessimistic (b)ET(a+4m+b)/6Variance σ2 =((b-a)/6)2ABCDEFG 274292210757113512712121948976712352.780.001.782.782.780.111.00The Project Schedule is for ETUsing PERT Start, 00000A, 912390B, 77070C, 62115159D, 71912169E, 12197197End, 024242424F, 324211815G, 524192419Earliest Start Time (ES)Earliest Finish Time (EF)Latest Start Time (LS)Latest Finish Time (LF)Activity Name & DurationSlack=LS-ES=LF-EF; Critical Path = Longest Path or Path with Least Slack!Can now answer additional questionsThe probability of finishing the project in 26 days?First, compute , where D = the desired project completion timeTE = expected completion time, i.e., the length of the critical path (sum of ETs for critical activities) σCP2 = variance of the critical path (sum of variances of critical activities)In our example, D= 26, TE = 24 and σCP2 = 0+ 2.78 +1 = 3.78. Then, Z= (26-24)/sqrt(3.78)=1.0287This corresponds to 84.8% (using a normal distribution table)2/)(CPETDZFindThe project duration corresponding to 95% confidence Start from same equation but now solve for D According to a normal distribution table, a Z of 1.65 corresponds to 95% probabilityThus, D= 24 + 1.65*sqrt(3.78)= 27.21
View Full Document