Unformatted text preview:

Chapter 5PERT AND CPM NETWORKSPowerPoint PresentationHistoryThe Language of PERT/CPMThe Language of PERT/CPM continuedThe Language of PERT/CPM concludedBuilding the NetworkTable 5-1 A Sample Set of Project Activities and PrecedencesFigure 5-1 Stage 1 of a Sample AON NetworkFigure 5-2 Stage 2 of a Sample AON NetworkFigure 5-3 A Completed Sample AON NetworkFigure 5-4 Stage 1 of a Sample AOA NetworkFigure 5-5 Stage 2 of a Sample AOA NetworkFigure 5-6a A Completed Sample AOA NetworkFigure 5-6b A Completed Sample AOA Network Showing the Use of a Dummy TaskTable 5-2 A Sample Problem for Finding the Critical Path and Critical TimeFigure 5-7 Stage 1 of a Sample NetworkFigure 5-8 A Complete NetworkFigure 5-9 Information Contents in an AON NodeFigure 5-10 The Critical Path and Time for Sample ProjectCalculating Activity SlackFigure 5-11 An MSP Version of PERT/CPM NetworkFigure 5-12 A Modified Version of MSP NetworkPROJECT UNCERTAINTY AND RISK MANAGEMENTCalculating Probabilistic Activity TimesFigure 5-13 The Statistical Distribution of all Possible Times for an ActivityActivity Expected Time and Variance95 Percent Level90 Percent Level95 Percent Level (Alternative Interpretation)90 Percent Level (Alternative Interpretation)Figure 5-14 An AON NetworkFigure 5-15 An MSP Version of a Sample Problem NetworkFigure 5-16 A Pert/CPM Network for the Day Care ProjectFigure 5-17 An MSP Calendar for the Day Care Project, 4/16/00 to 5/27/00The Probability of Completing the Project on TimeFigure 5-18 The Statistical Distribution of Completion Times of the Path a-b-d-g-hSelecting Risk and Finding DTHE GANNT CHARTFigure 5-23 A Gantt Chart of a Sample ProjectFigure 5-24 A Gantt Chart of Sample Project Showing Critical Path, Path Connections, Slack, EST, LST, EFT, and LFTFigure 5-25 A Gantt Chart of a Day Care Project Showing Expected Durations, Critical Path, Milestone, and Resource RequirementsFigure 5-26 A Progress Report on a Day Care Project Showing Actual Progress Versus BaselineEXTENSIONS TO PERT/CPMPrecedence DiagrammingFigure 5-27 Precedence Diagramming Conventions5-1Chapter 5Scheduling the Project5-2PERT AND CPM NETWORKS5-35-4HistoryLate 1950s–Program Evaluation and Review Technique (PERT)•U.S. Navy, Booz-Allen Hamilton, and Lockeheed Aircraft•Probabilistic activity durations–Critical Path Method (CPM)•Dupont De Nemours Inc.•Deterministic activity durations5-5The Language of PERT/CPMActivity–task or set of tasks–use resourcesEvent–state resulting from completion of one or more activities–consume no resources or time–predecessor activities must be completed5-6The Language of PERT/CPM continuedMilestones–events that mark significant progressNetwork–diagram of nodes and arcs–used to illustrate technological relationshipsPath–series of connected activities between two events5-7The Language of PERT/CPM concludedCritical Path–set of activities on a path that if delayed will delay completion of projectCritical Time–time required to complete all activities on the critical path5-8Building the NetworkAOA NetworkAON Network5-9Table 5-1 A Sample Set of Project Activities and PrecedencesTask Predecessora --b --c ad be bf c, dg e5-10Figure 5-1 Stage 1 of a Sample AON Network5-11Figure 5-2 Stage 2 of a Sample AON Network5-12Figure 5-3 A Completed Sample AON Network5-13Figure 5-4 Stage 1 of a Sample AOA Network5-14Figure 5-5 Stage 2 of a Sample AOA Network5-15Figure 5-6a A Completed Sample AOA NetworkE5-16Figure 5-6b A Completed Sample AOA Network Showing the Use of a Dummy Task5-17Table 5-2 A Sample Problem for Finding the Critical Path and Critical TimeActivity Predecessor Durationa -- 5 daysb -- 4c a 3d a 4e a 6f b, c 4g d 5h d, e 6i f 6j g, h 45-18Figure 5-7 Stage 1 of a Sample Network5-19Figure 5-8 A Complete Network5-20Figure 5-9 Information Contents in an AON Node5-21Figure 5-10 The Critical Path and Time for Sample Project5-22Calculating Activity SlackSlack or FloatLST - EST = LFT - EFT = Slack5-23Figure 5-11 An MSP Version of PERT/CPM Network5-24Figure 5-12 A Modified Version of MSP Network5-25PROJECT UNCERTAINTY AND RISK MANAGEMENT5-26Calculating Probabilistic Activity TimesThree Time Estimates–pessimistic (a)–most likely (m)–optimistic (b)5-27Figure 5-13 The Statistical Distribution of all Possible Times for an Activity5-28Activity Expected Time and Variance22E6)(Var6)(6)4(Tababbma5-2995 Percent LevelTask will be a or lower 5 percent of the timeTask will be b or greater 5 percent of the time3.3)( ab 5-3090 Percent LevelTask will be a or lower 10 percent of the timeTask will be b or greater 10 percent of the time6.2)( ab 5-3195 Percent Level (Alternative Interpretation)Task will be between a and b 95 percent of the time92.3)( ab 5-3290 Percent Level (Alternative Interpretation)Task will be between a and b 90 percent of the time29.3)( ab 5-33Figure 5-14 An AON Network5-34Figure 5-15 An MSP Version of a Sample Problem Network5-35Figure 5-16 A Pert/CPM Network for the Day Care Project5-36Figure 5-17 An MSP Calendar for the Day Care Project, 4/16/00 to 5/27/005-37The Probability of Completing the Project on Time2)(DZ=NORMDIST(D,,,TRUE)5-38Figure 5-18 The Statistical Distribution of Completion Times of the Path a-b-d-g-h5-39Selecting Risk and Finding D2ZD NORMINV(probability,,,TRUE)5-40THE GANNT CHART5-41Figure 5-23 A Gantt Chart of a Sample Project5-42Figure 5-24 A Gantt Chart of Sample Project Showing Critical Path, Path Connections, Slack, EST, LST, EFT, and LFT5-43Figure 5-25 A Gantt Chart of a Day Care Project Showing Expected Durations, Critical Path, Milestone, and Resource Requirements5-44Figure 5-26 A Progress Report on a Day Care Project Showing Actual Progress Versus Baseline5-45EXTENSIONS TO PERT/CPM5-46Precedence DiagrammingFinish-to-start linkageStart-to-start linkageFinish-to-finish linkageStart-to-finish linkage5-47Figure 5-27 Precedence Diagramming


View Full Document

UNCW OPS 472 - Scheduling the Project

Download Scheduling the Project
Our administrator received your request to download this document. We will send you the file to your email shortly.
Loading Unlocking...
Login

Join to view Scheduling the Project and access 3M+ class-specific study document.

or
We will never post anything without your permission.
Don't have an account?
Sign Up

Join to view Scheduling the Project 2 2 and access 3M+ class-specific study document.

or

By creating an account you agree to our Privacy Policy and Terms Of Use

Already a member?