Project Management in PracticeOutline:Overview:Schedule Variance & Cost/Spend Variance:Earned Value Chart 1Earned Value Chart 2Earned Value Chart 3Earned Value Chart 4Earned Value Chart 5Earned Value Chart 6Earned Value AnalysisTask Earned ValueTask Earned Value - ExamplesTask Planned Value/Cost, PVTask Planned Value/Cost, PV ExamplesVariances / IndiciesExampleExample AON Diagram:Gantt Chart:Excel Given & Solution:MSP Notes:Slide 22Slide 23Slide 24Slide 25Slide 26Slide 27Slide 28Project Control:Scope Creep & Change Control:Quality Management Processes The Big PictureSome Common Project Quality Tools/Data Collection:Check SheetsSlide 34Slide 35Pareto ChartCause-and-effect diagramSlide 38Slide 39Control ChartSlide 41Schedule VarianceCost VarianceProject Management in Practice 7-1Monitoring & Controlling the ProjectInitiateInitiatePlanPlanExecuteExecuteMonitorAndControlMonitorAndControlCloseCloseOutline:7-2 Overview Earned value analysis Project control / tracking techniques Scope creep and change control Quality / collection and presentation of project data.Homework: 25, 26, 27, 28#27 end of 6th week = MSP date 2/10/01 (end of 6th week), do not compute critical ratio use the default 5-day work week use start date 1/1/01#28 Repeat problem 27 using MSPOverview:7-3Project PlanProject PlanMonitoringMonitoringControlControlSchedule Variance &Cost/Spend Variance:7-4PVACEVPVACEVEarned Value Chart 17-5TimeNowDollarsSchedulevarianceCostvarianceCost schedule plan(baseline)ACWPBCWPBCWSActual costValue completed (Earned Value)PerformanceCostSched.badbadEarned Value Chart 27-6TimeNowDollarsBCWSbaselineACWPBCWP=EVPerformanceCostSched.badgoodEarned Value Chart 37-7TimeNowDollarsBCWSbaselineACWPBCWP = EVPerformanceCostSched.goodgoodEarned Value Chart 47-8TimeNowDollarsBCWSbaselineACWPBCWP = EVPerformanceCostSched.badbadEarned Value Chart 57-9TimeNowDollarsBCWSbaselineACWPBCWP = EVPerformanceCostSched.goodbadEarned Value Chart 67-10TimeNowDollarsBCWSbaselineACWPBCWP=EVPerformanceCostSched.goodgoodEarned Value AnalysisEarned Value Analysis compares the current project status with the original (baseline) plan.It computes several performance metrics for individual activities and for the entire project.It focuses on cost and schedule performanceIt’s a useful tool/input for project control.Popular project management software computes these metrics.Project EV is calculated by summing up the individual task EV’s.7-11Task Earned Value7-12Expert estimated value of work performed to date, if available.There are a variety of rules (see page 248).Work off budget / schedule values, if available.EV = BAC X (portion of work completed)EV = BAC X (actual work completed / total amount of work)Task Earned Value - Examples7-13Expert believes value of work performed to date is $120,000. Task is complete, expected to cost $1,500 (budgeted), best estimate is the task is 2/3 finished.Day 50 of 100 day, $100,000 budgeted task, manager estimated value of work performed is $40,000.Project X is at the end of its 5th week. Activity D is 30% complete. Activity D budgeted cost is $1000.D53 83Task Planned Value/Cost, PV7-14Budgeted / scheduled amount, to date.Determined from the baseline plan or budget.Works off budgeted cost numbers.BCWS.Planned cost of work on a task or project up to a given point in time.PV = BAC X (portion of time that has elapsed)PV = BAC X (time passed / total time scheduled)Task Planned Value/Cost, PVExamples7-15• Activity was scheduled to have spent $100,000 at this point in the plan / budget.• Work on a project task was expected to cost $1500 and the workers were originally scheduled to have the task compete today.• Work on a project task is uniformly distributed, total task budget is $2000. The task is scheduled to last 8 weeks, the current time is end of week 5. Task is scheduled to begin end of week 2.Variances / Indicies7-16Cost/Spending Varianceearned value (EV) – actual cost (AC)Schedule Varianceearned value (EV) – planned cost (PV)CPI (Cost Performance Index)earned value (EV)/actual cost (AC)SPI (Schedule Performance Index)earned value (EV)/planned cost (PV)Example7-17Day 75 of a 75 day task, Task “data conversion of payables for external vendors”.Task planned cost total on day 75, $100,000 ($100,000 = PV).Actual spend to date, $90,000.Best estimate 50% complete.Earned Value (EV) =0.50 X $100,000 = $50,000.Cost/spending variance = EV – AC = $50,000 - $90,000 = - $40,000.Schedule variance = EV – PV = $50,000 - $100,000 = - $50,000.CPI = EV/AC = 50/90 = 0.56 Cost Performance Index SPI = EV/PV = 50/100 = 0.50 Schedule Performance Index (we are worse on schedule than cost) ETC = (BAC – EV) / CPI = (100,000 – 50,000) / .56 = $90,000.EAC = ETC + AC = $90,000 + $90,000 = $180,000.ETC = Estimated cost To CompletionEAC = Estimated total cost At CompletionBAC = Budget At Completion AC = Actual Cost to dateExampleAON Diagram:7-18ActivityDuration (days)Preda 8 b 6 ac 4 4d 9 ce 11 af 3 bg 1 d,e,facbefdg0 819 204 1314 178 198 140 4Current date = end of day 18Gantt Chart:7-19Task eTask e = 11 days, current date is end of day 18At end of day 18, we are scheduled/planned to be 10/11 complete.This is used in the PV computation.Excel Given & Solution:7-204 4 4 4 4 4 4% of plannedActivityDuration (days)Budget ($) Actual ($) % Complete ES EFfinish on 2/1/01a 8 250 300 100.00% 0 8 1b 6 100 100 100.00% 8 14 1c 4 300 200 100.00% 0 4 1d 9 500 600 100.00% 4 13 1e 11 400 450 50.00% 8 19 10/11f 3 350 375 20.00% 14 17 1g 1 450 0 0.00% 19 20 0BAC $2,350.00 AC $2,025.00 EV $1,420.00 PV (budget) $1,863.64 4 4Current Date 2/1/01 For activity e notice the duration is 11 daysBeg of day 17 at the end of day 18, 1/11 is scheduled to remain (since the task EF is 19)End of day 18 10/11 of the task is scheduled/planned complete.4 4Project Start 1/15/01Cost/Spend var $(605.00)Schd var $(443.64)CPI 0.70 more has been spent than the baseline planSPI 0.76 given what has been spent, less progresss has been made than should have been4 4ETC $1,326.23 (BAC-EV) / CPIEAC $3,351.23 ETC + ACBreak task into 11 (its duration)parts. End of day 18 we are 10/11 finished.noticeMSP Notes:7-21Double ClickCurrent Date LineCurrent Date LineBeg of day 2/1End of day 2/1Used in MSPCalculationsPut end of day date here for MSP calculations7-22Enter activity names, predecessors,
View Full Document