Unformatted text preview:

RED HILL FUEL STORAGE TANKS J. David Rogers, Ph.D., P.E., R.G. Karl F. Hasselmann Chair in Geological Engineering University of Missouri-RollaFacts About the Red Hill Storage Tanks  Construction began Christmas 1940, completed September 1943  Project included 20 cylindrical tanks 100 feet diameter, 250 feet high  Design capacity of 6 million barrels fuel oil (255 million gallons)  Final cost: $42 million  16 men died during construction  Project also pumps 30 millions gallons per day of drinking water to surrounding areaFactors Leading to Construction  Prior to the attack on Pearl Harbor all of the Navy’s fuel was stored in unprotected above ground tanks at Pearl Harbor, next to the submarine base  When RADM Chester Nimitz was Commander of the Bureau of Yards & Docks (in 1940) he wanted the Navy’s 2-1/2 year supply of fuel oil protected from aerial attack  Standard practice was to dig a trench and bury the tanks, but this was impractical to store 255 million gallons of fuel oilInitial Plan  The Navy’s plan was to dig a series of tunnels and insert the tanks  Finding a suitable site was problematic, Oahu is underlain by the Koolau Volcanic series, and these flows are full of vugs, clinker, underground streams, and pools  Navy engineers finally settled on Red Hill, about two miles from Pearl Harbor, as it was mostly homogeneous basaltLocation of Red Hill and Pearl HarborRed Hill  Red Hill was not owned by the Navy, it was then under cultivation for sugar cane and pineapple plantations  The Navy leased the land, cleared and leveled it, then began construction of temporary work camps  Eventually the plantation owners were forced to sell out to the Navy through direct condemnation.Planning and Development  Consultanting engineer James P. Growden came up with excavating large vertical tank chambers instead of horizontal tunnels  This would increase the volume of material that could be excavated simultaneously and decrease the number of heavy equipment needed for hauling muck. It also decreased the unit cost for rock removal substantiallyDesign Concept for the vertically arrayed storage tanks Nothing like this had ever been attempted previously The contractor used gravity to “flow” rock muck to the base of each cavityVertically Aligned Cylinder Tanks  The tanks were set up in two parallel rows with two main access tunnels, one above the other, bisecting the rows  Smaller tunnels, or adits, branched from these main axis tunnels to the tank cavities.  To determine the depth necessary to protect the fuel from Japanese aerial attack, the engineers gathered data from the Army, multiplied it four-fold and rounded the figure off to 100 feet of rock coverSidehill entrance to the tank excavations and lower access tunnel, as sketched during constructionAccess Tunnels  Once the tank invert level and radius of curvature were determined digging could commence.  Both the upper and lower access tunnels were excavated simultaneously  They were constructed like the horseshoe shape of railroad tunnels, flat floors and walls, with an arched ceiling  The tunnels were rough hewn then lined with concrete for increased strengthChamber Adits  As the main access tunnels moved past the location of an proposed storage chamber, more workers began digging the branch lines, or horizontal adits  The adits were smaller, man sized, and were shored with steel H-beams bolted together and sprayed with cement  The lower adit was excavated as far as the center point of the tank and the upper adits were stopped when they reached the outer radiusBeginning Tank Chamber Excavation  In the upper adit, once the outer radius of the tank had been reached, a ring tunnel was dug around the radius of the tank chamber  Upon completing the ring tunnel, the miners dug upwards in a hemisphere from all points around the ring, narrowing as they reached the central shaft  Meanwhile, a central shaft 8 feet in diameter was excavated through the central axis of the chamber, down to the lower aditHow Each Chamber Excavation Began The upper dome of each fuel chamber was excavated first, starting with a ring tunnel, then working upward, towards the central shaftForming the Upper Dome (1 of 2)  Each section of the dome had to be braced with timber, prefabricated above ground in the exact curvature of the dome  This allowed the miners to dig to a template reducing time of excavation  I beams were then sent down and assembled to form ribs around the dome  Sections of steel plate cut to piece together and form the dome were sent down and welded togetherForming the Upper Dome (2 of 2)  The wood shoring had to be shortened and replaced to account for the H-beam steel sets and liner plates  A pipe network extending down the central shaft and radiating around the dome was constructed for placing concrete to line the tank chambers  Each chamber dome required 70 hours of continuous pouring for 5000 cubic yards of concreteAfter the upper hemisphere dome was concreted, miners could begin mucking the upper tank chamber, dropping muck by gravity through the central shaft, as shownTank Excavation (1 of 2)  As soon as the upper hemisphere concrete had set, workers were lowered down the central shaft to begin excavation of the tank chamber  The miners dug outwards in all directions under the dome, keeping a 30 – 45 degree slope to the center of the shaft, so muck would slide into the shaft by gravity, greatly reducing mucking labor and transport for the project  At the bottom of the vertical shaft rock screens (grizzlies) broke up falling rock so it could be transported on conveyorsTank Excavation (2 of 2)  In the lower adits an elaborate conveyer belt system was constructed to carry mucked rock out of the excavations  The central tank shafts were expanded in a cone under the upper dome until the desired diameter was reached  Following the deaths of a few workers falling down the central shaft, planks were rigged to the dome for them to stand onSketch of a tank’s lower hemisphere under construction being lined with concrete with an inner steel liningFinishing Excavation  The miners continued to dig downwards in a cone until they reached the lower hemisphere of the tank chamber  The lining for the lower hemisphere was placed similarly to the top  Any cracks or holes found during excavation were grouted


View Full Document

Missouri S&T GEO ENG 342 - Red Hill Fuel Storage Tanks

Documents in this Course
Load more
Download Red Hill Fuel Storage Tanks
Our administrator received your request to download this document. We will send you the file to your email shortly.
Loading Unlocking...
Login

Join to view Red Hill Fuel Storage Tanks and access 3M+ class-specific study document.

or
We will never post anything without your permission.
Don't have an account?
Sign Up

Join to view Red Hill Fuel Storage Tanks 2 2 and access 3M+ class-specific study document.

or

By creating an account you agree to our Privacy Policy and Terms Of Use

Already a member?